The CGN Solar Delingha 50MW parabolic trough CSP plant is one of China’s first  batch of demonstration CSP projects and leads the construction progress. The project has a total investment of 1.938 billion yuan and is equipped with 9 hours of molten salt heat storage. Once completed, CGN Solar Delingha 50MW parabolic trough CSP plant will be the first commercial parabolic trough project and the first operational demonstation CSP project in China.

Project Overview:

Project Schedule

● June 30, 2018,connected to the grid
● December 2017, HTF Island started operation
● December 2017, entering heat transfer oil injection phase and turbine low pressure casingsuccessfully capped
● November 2017, 90% of solar fieldcompleted
● September 2017, turbine generator rotorhoisted into position
● August 31, 2017, factory was successfulin receiving electricity
● June 29, 2016, the main transformer wasinstalled in place
● April 2016, HTF & TES startedconstruction
● July 2014, broke ground officially
● February 2013, approved by the localQinghai Province government
● July 13, 2012, signed MoU withAsian Development Bank on CSP project
● April 2012, CGN solar energy establishedthe experimental base of CSP technology