Due to the absence of 4 projects on the list of China’s first batch of 20 CSP demonstration projects, the total installed capacity of China’s demonstration projects has decreased to 1014M. The 16 projects that have promised to continue construction have fully resumed or been speeding up the work of preliminary development.

The follows are a summary of the latest construction progress of China’s first batch of CSP demonstration projects.To know more details about rhe construction situation of China’s first batch of CSP Demonstration Projects, please participate in the China International CSP Station Conference & CSPPLAZA 2018 Annual Conference

1.Shouhang Saving Dunhuang 100MW Molten Salt Tower Solar-Thermal Power Generation Project

The project is planned to be completed and put into production by December 31, 2018. To February 4, 2018, the ceiling of the heat-absorbing tower has been lifted to 235 meters high. Currently, the steel structure inside the heat-absorbing tower is under construction and the installation of 1,650 columns has been completed in the heliotat field.

Picture: Masonry of the main carven’s wall

Picture: Installation of heliostat field’s columns

Picture: Thermal storage tank under construction

2.Supcon Delingha 50MW Molten Salt Tower CSP Project

The project is planned to be completed and put into production by December 31, 2018. The construction resumed on March 7th, 2018. Up to now, the heat-absorbing tower has been poured to a height of about 90 meters and the installation of about 7,200 sets of columns has been completed in the heliostat field. A total of nearly 6,000 mirrors have been installed.

Picture: frame assembly

Picture: cold salt tank

Picture: hot salt tank

Picture: heat-absorbing tower

3. China Guangdong Nuclear Solar Delingha 50MW parabolic trough CSP Demonstration Project

The project promises to achieve the completion before the end of 2018. Currently, the construction work and the installation of the equipment have been basically completed. It is expected that the first grid connection can be realized by the end of June 2018.

4.Yumen Xinneng 50MW Molten Salt Tower CSP Project

The project aims to be put into production before the end of 2018. At present, the welding assembly of the secondary reflector tower’s pylon and the installation of the heliostat are in progress.

5.Gansu Axe Jinfan Energy 50MW Molten Salt Parabolic Through Solar-Thermal Power Generation Project

The project will strive to achieve grid-connected generation by the end of 2018 to ensure to be totally completed and put into operation before June 30, 2019. At present, the project has completed all the pouring tasks of the solar field and more than 700 collector stands have been installed.

6.China Power Engineering Consulting Group Northwest Power Design Institute Co., Ltd. Hami 50MW Tower Molten Salt CSP Demonstration Project

The project is planned to be put into operation before June 30, 2019.

Picture: Construction of front area of the plant

7.Qinghai Gonghe 50MW Molten Salt Tower CSP Project

The project will strive to be combined to the grid by June 30, 2019 and ensure to be completed and put into operation before December 30, 2019.

8.Inner Mongolia Zhonghe Longteng New Energy CO.,Ltd Urat Middle Banner Conduction oil Parabolic Through 100MW Solar-Thermal Power Generation Project

The project is planned to be completed and put into operation before the end of December 2019. At present, the project has completed field level construction.

9.Changzhou Royal Tech 50MW Trough CSP Project

The project is planned to be completed and put into operation before the end of December 2019. The construction work will be formally launched in April. At present, the preliminary work of the project has been basically completed and obtained permission of the local government to start construction and the preliminary assessment of the initial design has been completed by the Electrical Planning and Design Institute.

Picture: delivery of silicone oil

Picture: Turbine high pressure cylinder rotor and outer cylinder are under intense machining

10.Rayspower Yumen Dongzhen 50MW Parabolic trough CSP Demonstration Project

The project plans to achieve grid-connected power generation by June 30, 2019. At present, it has not yet been fully constructed.

11.Lanzhou Dacheng Dunhuang 50MW Molten salt Fresnel CSP Demonstration Project

The project plans to achieve grid-connected power generation by June 30, 2019. At present, it has obtained preliminary formalities such as environmental assessment, and the tendering and procurement of major equipment has been successfully completed. Bidding of other ancillary equipment is in progress.

12.China HuaQiang Zhaoyang Zhangjiakou 50MW Improved Fresnel Solar-Thermal Power Generation Project

The project is planned to be completed and put into operation by the end of 2019. Currently, it has not yet fully broken ground.

13.Zhongyang Chabei 64MW Molten Salt Trough CSP Project

The project promises to complete all the construction between June and October 2019 and all the commissioning work by the end of 2019, and realize grid-connected generation on time. Currently, it has not yet fully broken ground.

14.Dahua Shangyi 50MW Tower Solar-Thermal Power Generation Demonstration Project

The project is planned to be completed and put into operation by the end of 2019. Currently, it has not yet fully broken ground.

15.Three Gorges New Energy Co.,Ltd. Jinta 100MW Tower CSP Demonstration Project

The project promises to achieve completion by the end of 2020. Currently, it has not yet fully broken ground.

16.Zhongjieneng Gansu Wuwei Solar Power Generation CO.,Ltd Gulang Conduction oil Parabolic Through 100MW Solar-Thermal Power Generation Project

The project promises to start construction before June 30, 2018 and achieve grid connection before June 30, 2020.

17.Guohua Yumen 100MW Molten Salt Tower CSP Project

The project explicitly quit.

18.State Power Investment Co. Huanghe Hydropower Development Co., Ltd. Delingha 135MW CSP Demonstration Project

The project did not make a promise on schedule.

19.Huaneng North United Power Co.Ltd. Urat 50MW fresnel CSP Demonstration Project

The project did not make a promise on schedule.

20.Zhongxin Zhangbei New Energy Development CO., Ltd 50MW Fresnel Solar-Thermal Demonstration Power Station

The project did not make a promise on schedule.